Yesterday, June 13, the Secretary of State for Energy, Engineer Arlindo Carlos, carried out a technical visit to the construction fronts of the Electrification Project of the Villages of Calulo and South of Conda. He was received at the Municipal Administration of Libolo by Administrator Rui Miguel and Enerline staff, where the project was presented by our colleague Márico Kassuca, Project Director.

The purpose of the visit was to assess the progress of the works and the situation of other communities in Calulo that have not yet been reached by electricity.

The visit continued with an inspection of the conditions of the Calulo substation and subsequently the distribution line construction sites, before moving today towards Kibala.

It is expected that this project will reach 98% completion by December of the current year, and that energy access in this region can be further expanded with other projects.